Technical Demolition Services were commissioned to carry out the demolition & deconstruction of two redundant gas holders on Hind Street, Birkenhead, for National Grid Property Holdings Limited.

The demolition of the decommissioned gas holders & clean-up of the surrounding land is part of National Grids commitment to bringing redundant sites back into use.

Works were carried out using X3 944 Liebherr machines fitted with attachments & a 906 Liebherr attached with magnet & grapple.

Client: National Grid Property Holdings Limited

Contract: Decontamination, Demolition & Asbestos Removal

Contract Start/End: 2017 – 2018

Contract Value: £500,000.00

Scope of Works

The various works included;

  • Demolition & deconstruction of two redundant gas holders; one below ground spiral guided gas holder & one above ground spiral guided gas holder.
  • De-watering & de-sludging under controlled discharge conditions, working with a specialist sub-contractor.
  • Removal of non-notifiable & notifiable asbestos containing materials.

Project Challenges

  • Minimising environmental noise, dust & vibration to protect employees, neighbouring properties & adjacent rail line.
  • Close liaison with Network Rail was essential due to the close proximity of a live rail line.
  • A ‘live’ pressure reducing station was present on site and only a matter of metres from the workface. Carrying out the works required close liaison with National Grid & Cadent engineers, ensuring prior approval was obtained.

Neighbours

The site was surrounded by both commercial & residential properties and to the north a live railway station. TDS worked closely with all stakeholders to ensure minimum disruption throughout the works. 

Completion Report

As with any contract completed, the project manager will issue the client with all relevant documentation:

  • As demolished drawings (superimposed over footprint of the site)
  • All service capping locations
  • All services that remain in the ground on completion of project
  • Other uncovered structures/ apparatus discovered during foundation removal
  • Location of adjoining structures
  • Completed construction phase plan
  • Copies of all risk assessments and method statements (final revisions)